Well we've ground to a halt here as the delivery from kitchen suppliers (which came last week) is missing loads of stuff. They also supplied the dreaded 30cm "can't fit a dinner plate in" wall units despite the plan having 32cm written in RED on it. Sadly we didnt notice until after fitter had put them up. But supplier is sending the right ones.
Only half the appliances are here and crucially we are missing the wine rack which sits between wall and big larder, so they can't fit that.
I'm glad I used the supplier's fitters as they are sorting it out.
The fitters are wonderful, they're doing a beautiful job and have reassured me that I will get the kitchen I wanted... Eventually.
This delay won't really affect the final end point as we have a hiatus next week anyway while we wait for quartz to arrive. Thankfully they've done enough that the templating can still be done tomorrow as planned.
It's more frustrating for the fitters, they are doing this for a fixed price based on a certain number of days and it's now going to take longer. They have told me that they will charge the extra days to the supplier and not to me.