@WhereDoesThisToiletGo You can absolutely ask them, and they are likely to be able to give you one - all estimates and flexible but it will give you an order in which they do things. We had one and it really help - it also help me know when I needed to make decisions! Ours provided us with this:
December, Monday 3rd until Friday 7th.
- Brickwork and steel work continued.
December, Monday 10th until Friday 14th.
- Brickwork and steel work continued.
- Decision on windows and skylight so we can order them in good time.
December, Monday 17th until Friday 21st.
- Climax to steel work and brickwork.
- Shut down tidy up.
- TWO WEEK SHUT DOWN BUT WE MAYBE CARRYING ON BETWEEN CHRISTMAS AND NEW YEAR. TO BE CONFIRMED.
January, Monday 7th until Friday 11th.
- Brickwork and steel work snagging.
- Roof construction.
- Install UPVC windows and doors.
- Decision on kitchen and flooring if it’s not been already made.
January, Monday 14th until Friday 18th.
- Completion of roof structure and 1st fix carpentry. Studwork/door linings/noggins.
- Roof coverings.
January, Monday 21st until Friday 25th.
- Completion of roof coverings.
- Knock through walls.
- 1st fix electrics. Cabling to new areas.
- 1st fix plumbing. Kitchen, heating.
January, Monday 28th until February Friday 1st.
- Plastering.
- Concrete screeding to extension.
February, Monday 4th until Friday 8th.
- Carpentry 2nd fix. Hang doors, flooring, skirting,architrave.
- Decoration.
- 2nd fix electrical.
- 2nd fix plumbing.
- Start kitchen/utility.
February, Monday 11th until Friday 15th.
- Kitchen installation.
- Decoration.
- 2nd fix electrics.
- 2nd fix plumbing.
February, Monday 18th until Friday 22nd.