So all went well for first 2 months. Ahead of schedule.
Architect monitored and confirmed regular valuations.
Then any variations became very highly priced
Then windows paid for not delivered
Turned out when we asked for proof of order (given none appearance and cash in advance) than they were only just ordered.
Ditto floor.
Now the work on site has slowed to almost snails pace.
Only plasterer there today.
Only electrician other day.
Was forecast to run 6 weeks late a week ago.
On Friday that was revised to 8 weeks.
What had been agreed was that we would move back 2 to 3 weeks before completion and remaining work would be external or around us.
What best to do?
There are penalties in contract but it seems to have no effect.