Meet the Other Phone. A phone that grows with your child.

Meet the Other Phone.
A phone that grows with your child.

Buy now

Please or to access all these features

Property/DIY

Join our Property forum for renovation, DIY, and house selling advice.

Line of junction notice - starting works

3 replies

flowerpothead · 23/12/2016 03:12

We have served a line of junction notice to our neighbours for our extension which is being built up to but not on the boundary. I know we have to wait a month before digging foundations or starting to build but can we start demolishing the existing garage a couple of days early - the builders would like to start on a Monday. Thank you!

OP posts:
Tatey25 · 26/12/2016 00:15

If the demolition work involves a wall of a building up to or astride the boundary with a neighbouring property, work on an existing party wall or party structure or building against such a party wall, party structure or excavating near a neighbouring building the demolition works might fall within the party wall Act, which means you will have to wait until the notice period has expired otherwise the adjoining owners can seek to stop the works through a court order.

flowerpothead · 30/12/2016 00:55

Great, thank you. Will get them to start on internal stuff.

OP posts:
johnd2 · 30/12/2016 09:55

You don't have to wait a month, that's only if they don't agree you can start earlier. We put a tick box for starting straight away and of next door ticked it.
In the end it was a month before we started anyway, but at least it was all sorted.

New posts on this thread. Refresh page