We are planning a simple (so the architect says) single storey extension. We are keen to start building ASAP so Building Notice route of 48 hours seems preferable to submitting Full Plans route that can take up to 8 weeks. are we naive wanting to go the Notice route? I know we'd need to ensure our builder was up to date with building control regulations etc & get it written everything to be included in the quote. What do you think?