The builder has just dropped the bombshell that the screed in the extension needs three months to dry before you can lay flooring on top. Google has confirmed this (1mm per day, it's a "standard" 75mm depth). We can't install the kitchen before the floor has been laid...
So how the jeff do people get extensions completed in less than say, four months? It's taken three months to get to this stage (ready for the screed to go in) already! Am I supposed to wave goodbye to the builders for three months while my floor dries and sit there with an empty room?
My kitchen is currently sitting in a damp garage getting slowly ruined 