Project Managing renovation and extension. Need a Construction Project Plan Template

43 replies

Gantt · 26/11/2023 14:27

I mm project managing the renovation and extension of our 4-bed Victorian house. Builders are starting shortly and I need to produce a construction phase / project plan of some sort - something that shows (a) when each task should start and finish and (b) how work interfaces with other things, i.e. electrical first fix before kitchen installed, etc.

Has anyone project managed something like this and what kind of template did you use?

OP posts:
New posts on this thread. Refresh page
Nofilteritwonthelp · 27/11/2023 21:15

Gantt · 26/11/2023 18:24

@Nofilteritwonthelp what is the difference between the project plan and project schedule?

A plan is like is the who, what, when, why, risks etc. A schedule is the timeline, the task, dependencies etc. As PP said, there's a reason it's a profession. Also most people who think they project manage actually don't, it's a very overused word. You should engage someone who knows what they're doing. I predict a huge budget blow out if you're on mumsnet and google trying to figure it out, get someone who actually knows what they're doing. Good luck.

Unescorted · 26/11/2023 21:37

If you are unsure then take independent legal advice. Or take a punt and run with what you have. No one here can advise you in any meaningful way on your project compliance.

Gantt · 26/11/2023 21:33

We also have full construction and renovation insurance in place, as does our contractor (public liability)

OP posts:
Gantt · 26/11/2023 21:29

For the extension build I definitely feel we need the architect to look over the work. However Building Control will also be checking construction and anything structural.

I don't think any liability rests with private BC firms however - might be different for Local Authority BC.

For the renovation, I've managed one before and know what I'm looking at in terms of workmanship and materials used etc.

OP posts:
Gantt · 26/11/2023 21:24

Unescorted · 26/11/2023 18:38

Then you need to employ some one to act as your employers agent - normally the architect/ design side person to ensure the builder / contractor is building to standard and getting the correct building control sign offs.

You also need to ensure that your contractor is undertaking CDM duties (all the bits in the PP that aren't the schedule of works). Until you appoint them in writing and they agree to take on the duty it will remain with you.

The correct building control sign offs will happen as we have a private BC firm involved who are sending me schedules at every step of what they need and when they will do site visits to sign off.

The 'building to standard' is something our architect will monitor with ad hoc site visits along the way, to check on construction.

OP posts:
Fieldofbrokenpromises · 26/11/2023 21:19

Gantt · 26/11/2023 15:37

I don't - I manage contracts and procurement for a construction firm

and you're asking Mumsnet for advice?

Unescorted · 26/11/2023 21:16

I can't say as I am not sighted on the JCT... There are several types. If in doubt ask them if they are taking CDM duties. The link I put earlier gives more details.

Gantt · 26/11/2023 21:13

@Unescorted Our contractor has signed a JCT contract but I don't think undertaking CDM duties was included in that. Is this a separate legal agreement?

OP posts:
WithManyTot · 26/11/2023 18:49

Gantt · 26/11/2023 18:32

It's a schedule of works that I need to develop

A "Stacked Bar Graph" in Excel 'can' do this for you. You make the first series Start Date, and make the bar invisible. The second series is Duration, and make that show...

However!!!

It's very static and the first time something changes, and it will, you have to manually adjust everything.... which is why even for just producing a schedule a proper to0l is best

Unescorted · 26/11/2023 18:38

Then you need to employ some one to act as your employers agent - normally the architect/ design side person to ensure the builder / contractor is building to standard and getting the correct building control sign offs.

You also need to ensure that your contractor is undertaking CDM duties (all the bits in the PP that aren't the schedule of works). Until you appoint them in writing and they agree to take on the duty it will remain with you.

Gantt · 26/11/2023 18:32

It's a schedule of works that I need to develop

OP posts:
Unescorted · 26/11/2023 18:30

Project plan includes who is responsible for what, risk management strategy, who is doing what when & who has control of the site at each point of the project ect..

Schedule of works is what trades are on site when.

Gantt · 26/11/2023 18:24

@Nofilteritwonthelp what is the difference between the project plan and project schedule?

OP posts:
Gantt · 26/11/2023 18:22

We have a main contractor who is happy to work with me directly. He's aware I'm not an experienced construction PM.

OP posts:
Torganer · 26/11/2023 18:16

You will also need a sense check for durations. Otherwise the subcontractor could quote you excessive durations. They do this to main contractors, so god knows what they would say to someone they know has now experience in PM.

Torganer · 26/11/2023 18:13

You can definitely use excel for construction planning though. On a large £1bn+ project we would have the main programme in P6, and then do the 4-weekly in excel to package plan. If you’re good at excel it’s very easy to construct a programme including Gantt chart.

Torganer · 26/11/2023 18:10

Primavera is total overkill for a 10month house renovation - we use it for £billion infrastructure projects!!! The licence alone would be prohibitive.

Are you planning all the works, or is there a main contractor? Get a programme from all the subcontractors. You’ll need to know what can be done concurrently and what need to follow what (the critical path). Don’t forget to factor in material lead in times.

If you have a main contractor, get them to do the programme and then you can just tick things off. If you don’t have construction experience there is little point in you doing the programme as you won’t know the sequence or tasks.

WithManyTot · 26/11/2023 18:07

I'd use ...err.... MS Project, because that's what it's designed for. If I had a big long list of numbers to add up, I'd use Excel. If I wanted to write a letter I'd use Word. Once you have the right tool it's a lot easier..

If you're just listing some activities as a schedule , with specified start and finish dates, as someone else has already done the project planning activity for you ( the architect and contractor?) then just pop the titles and dates in Project, print it out on A1 and tape it to the wall, Job done...

Unescorted · 26/11/2023 17:54

https://www.hse.gov.uk/pubns/indg411.htm

I would recommend reading the HSE guide to CDM regs so you at least understand what documents you need in place. At least to appoint you CDM person correctly so they can draw up the construction plan... And hopefully keep everyone safe on site.

Need building work done? - A quick guide for clients on the CDM Regulations 2015

Practical guidance on complying with new regulatory duties in construction.

https://www.hse.gov.uk/pubns/indg411.htm

Nofilteritwonthelp · 26/11/2023 17:54

Plmnki · 26/11/2023 16:20

There’s a reason why project managers are a separate discipline and get paid got their skills and knowledge. You can’t download that as a template.

Pay a professional to manage this work because it certainly won’t get done to time, quality or budget if the PM role is in the hands of an amateur.

This. Also do you mean a project plan or a schedule as they are two very different things

Good4you · 26/11/2023 17:51

If you’re looking for an accurate timeline of when what will be done and what needs ordering you will need a programme not a CPP

Good4you · 26/11/2023 17:50

And utility information before the health and safety goals with any floor plans that show this in your appendix

Good4you · 26/11/2023 17:48

Can’t really send my CPP as it’s my company’s template.
front page - project name and location
contents
distribution list
revision list
project scope with start date and estimated finish date
project team list
communication tactics between companies - how often do you want communication do you want a daily shift report and weekly overview?
method statements - your work package plans that break down each task -site enabling, demobilisation, electrics, mechanical, building etc. (ask the construction company)
and then the health and safety goals but I’m guessing you can ask the health and safety person for this?
fire plan
emergency plan (police number / where’s the closest hospital)
any risks associated with the work will have to be mentioned and how you would manage these risks i.e falling from height, lifting heavy objects etc.
appendix with any house surveys and a risk assessment

Unescorted · 26/11/2023 17:45

Excel 365 has a simple Gantt chart template.
No template is going to give you the knowledge/ experience to pm a construction project. It is a bit more than knowing when to order up the fixtures and fittings.

Gantt · 26/11/2023 17:38

The architect is on hand for queries and our contractor is very experienced. All trades (all elements of the work) fall under the one contractor. It’s really just a case of making sure timelines are kept to and a tool for me to make sure I order fittings / fixtures at the right times

OP posts: