To feel so foolish for underestimating house renovation timescale

93 replies

Eastie77Returns · 08/05/2022 13:25

Apologies this is long:((

We bought our house in March. I had a number of ongoing threads for months as there were so many ups and downs so felt incredibly relieved when we finally Completed.

It is a 3/4 bed semi and I knew it needed work when I first viewed back in September but only had a vague understanding of the level required. The survey/report didn’t flag any major issues so I told DP that we should move in upon completion and just renovate as and when.

When we went for the pre-exchange viewing in Feb (the first time I had seen it since September) it became apparent the kitchen and bathroom would have to be ripped out as they were in an awful state. The vendor was an older woman with significant mental health issues and the place had been left to wrack and ruin. Despite this I was misguided enough to give our landlady 2 months notice as I thought the house would be liveable in that time. DP, who has actually renovated houses before said nothing to dissuade me.

So we move out next week and the situation is this: bathroom is done but we are looking at least another 3 months for the rest. The rest of the house needs to be plastered, ceilings still to be taken down, complete rewiring, new flooring has been ordered and has a 4 week lead time and can’t be laid until plastering etc is done. I agreed to DP’s suggestions without understanding the timeframes such as moving the boiler into an exterior utility room which will take a several weeks as we wait for the engineer to remove and install the new one.

We will now have to stay with my parents which I am absolutely dreading (that’s a whole other thread). Kids schooling is up in the air as their new school is several miles from parents so would be easier to keep them at current school around the corner but think I have to move them now or loose the places.

I frequently feel like crying and wake up each day feeling anxious and stressed. I also completely understand this is a first world problem and there are millions of people with real and bigger problems than me.

Thank you if you’ve got this far. I’m just venting at my foolish naivety really and also hoping for some success stories from anyone whose renovations actually happened a lot quicker than they thought?

OP posts:
Netaporter · 29/07/2022 11:17

@Eastie77Returns wtf? I’d be reporting that to British Gas.

Eastie77Returns · 29/07/2022 10:59

Netaporter the builder and structural engineer said building regs sign off was not needed due to the nature of the internal wall that was removed. I contacted Building Control in my borough to verify this and request a site visit. The officer I spoke with set up a ‘virtual site inspection’ with photos and videos as he said a domestic project of my size would not require on site. He concluded that Building Regs were not required. However I’m now concerned I should have got some kind of official documentation attesting to this as there may be issues if/when I sell?

Today I'm holed up in the front room trying to work. The British Gas contractor who messed up the pipework is here. He is very surly and clearly annoyed at being called back. I explained that our cooker could not be installed due to the error. He sneered and said I should have insisted that the fitter from AO dealt with it "but you women never know how to handle these things properly". Urggh.

In contrast we have a lovely floor fitter in finishing the installation upstairs. So friendly and has taught the DC how to count to 10 in Romanian (although we now have to hear this on repeat from both of them throughout the day...)

OP posts:
Netaporter · 28/07/2022 16:15

@Eastie77Returns do you have the building regs sign off/compliance and paperwork for the works that brilliant builder did though? You need to get that for sure.

renovations you live in are a bit like childbirth. terrible at the time, soon forgotten. Keep buggering on!

WeRTheOnesWeHaveBeenWaitingFor · 28/07/2022 11:24

How sweet to care about worrying me when your going through all this. You’ll have to post some pics of the fabulous results when it’s all done.

Eastie77Returns · 27/07/2022 12:48

@Netaporter Thanks for all these tips. The frustrating thing is I tried to follow a lot of what you advise. We were undone by a builder who turned out to be completely incompetent despite multiple recommendations and allegedly decades of experience.

We had a wall removed right at the start. We worked with a structural engineer who did all the required steel/beam calculations and a brilliant builder who had carried out hundreds of similar wall removals. All went well at this point and I don't think there will be an issue with building regs for that work.

If we had continued with brilliant builder I think we would have been home and dry by now but he had to travel abroad and so recommended nightmare builder, a longstanding friend of many years.

Nightmare builder and his tradesmen had a detailed kitchen plan but they complained (after the installation) that it was not very clear. They should have def. been aware of the rules around required distances for the switches etc.

The British Gas engineer has acknowledged they messed up with the pipework but they can't get out to fix it until next week so we have another week of no cooker.

There has just a lot of incompetence all round.

We now have all switches and radiators installed.

And yes, we have Cortex over every inch of the flooring already installed downstairs:)

At least I can say I've learned a lot from this experience. I will never renovate a house again.

OP posts:
Netaporter · 27/07/2022 04:57

@Eastie77Returns what a nightmare you’ve had. I can’t recall, have you done any structural work? Removed walls etc? Your insurance against mistakes should’ve been mitigated by building control (who work for you to spot any incorrect work that fall foul of building regs). You’ll also need sign off by them for when you come to sell if this does apply. Any qualified electrician or plumber should also be fully aware of the rules surrounding switches/sinks etc so unless no one gave them a plan for each room (particularly the kitchen layout) this is unusual. British Gas tradesmen absolutely should be aware how to fit a pipe to accommodate a range correctly.

Moving forward, literally draw out every room not yet finished and be exact with the new builder and each contractor about exactly where every switch/lightfitting/cabinet/radiator is to go. To the last mm. Your builders will thank you and you’ll feel more in control. I usually tape a laminated plan on the door of each room and also a checklist of the items i’m supplying /the contractor is supplying for each room and their location on site.

good luck with the flooring. Although I understand the need to have dust-free floors, you are still having work done and the chance of dirt being walked into your new floor covering is high. Invest in corex/carpet protector and cover it until you are sure every trade has left the room. And buy over boot covers and leave them buy the front door. Unless you are specific, tradesmen will not take their shoes off, nor think ‘I won’t drill here as there is a pile of washing/soft furnishings/new carpet next to where I want to drill so will move that first’ 😭

Eastie77Returns · 26/07/2022 23:22

WeRTheOnesWeHaveBeenWaitingFor · 26/07/2022 22:01

I’m in the middle of a house renovation and I’ve just come across your thread, It’s giving me anxiety just reading it. Thank god you are at the final stages. Where have you been staying?
Just think about how much you will appreciate your new kitchen etc when it all works.

We completed on the house in March and stayed with my parents for a while and then found an Air BnB around the corner. We’ve been living in the house for about 3 weeks now. Sorry this has made you anxious. I think I was extremely unlucky with my crazed builder and I hope what I’ve been through with him is a rare occurrence. He was recommended by our brilliant first builder and our new neighbours. They’ve since told me he had a bad fall and fractured his skull
whilst on a job a couple of years ago and “hasn’t been quite right since”. There are clearly some mental health issues. They all feel very badly about how things have turned out.

The other issues that have cropped up including todays cooker debacle are part and parcel of renovating I think. All in all I can’t hide the fact the last 3 months have been a bit shit but I’m seeing a light at the end of the tunnel and our new builders have slowly restored my faith somewhat in tradesmen.

OP posts:
WeRTheOnesWeHaveBeenWaitingFor · 26/07/2022 22:01

I’m in the middle of a house renovation and I’ve just come across your thread, It’s giving me anxiety just reading it. Thank god you are at the final stages. Where have you been staying?
Just think about how much you will appreciate your new kitchen etc when it all works.

Candleabra · 26/07/2022 21:38

Keep going, you’re making progress now.
il sorry to hear the original builder was such a nightmare.

Eastie77Returns · 26/07/2022 19:31

We have a half functioning kitchen. Small steps. The plumbing is done and the sink and dishwasher work.

However today was the second unsuccessful attempt to have our Range cooker from AO.com installed. First time failed as the cooker switch was not the required distance from the hob. This was the fault of Psycho Builder (he also messed up some of the kitchen cabinet installations so there wasn't enough space to even put the cooker in ffs). New builder rectified the issues but today's problem was to do with a pipe fitting on the wall behind where the cooker will be installed as it sticks out a few inches too far. This pipe was put in by British Gas who will now have to come back out and fix it.

Kitchen light fittings arrived this morning. Some of the pendants were the wrong size (too small). The company I ordered from forgot to include a Returns label so I bit the bullet and drove an hour to their showroom to return in person and buy the next size up. They were extremely apologetic and doled out biscuits and tea while I waited in their cavernous warehouse for the new pendants so all is forgiven. I'm so easily placated.

Flooring guys are in tomorrow to start part two of the floor installation upstairs. They were meant to start in 2 weeks but called today to say the material unexpectedly arrived early and can they start now? The upstairs rooms are not really cleared/ready but I'm actually desperate to get this bit done so we are no longer walking on dusty floorboards so this evening we are clearing out as much as we can.

I need a glass of wine.

OP posts:
Lulooo · 22/07/2022 03:01

I just want to add that I doubt there have many renovations in the world that didn’t go past the deadline and didn’t go over budget.

Building works and home upheavals are stressful. Don’t beat yourself up more what guilt and regret.

Oblomov22 · 22/07/2022 02:45

Sorry to hear this. No surprise. 2 of my bil are builders and I could tell from the start. Hope you get it sorted.

Netaporter · 22/07/2022 02:24

@Eastie77Returns glad to hear things are getting back on track! Sounds like you’ll be able to put the dealings with psycho builder behind you shortly 🤞

Impier · 21/07/2022 19:57

I'm a project manager, and just started a job where I have had a couple of houses to renovate, as well as some much bigger projects.

First project, new kitchen, new bathroom, new carpets/flooring, garage conversion, knock through for kitchen/dinner, fully painted throughout. Total time five weeks, competing in time tomorrow.

Second project, old farm building. Uninhabited for 5 years. New kitchen, new bathroom, replaced rotten floor joists, new floor boards, new electrics, new central heating, loft insulation, replaced plaster, redecorated throughout, new carpets/fitting throughout. It's in a conservation area and we worked around bats under the supervision of an ecologist. Six week to do this, finishing on Wednesday, 3 days late.

If you need a job doing, get a professional in.

Eastie77Returns · 21/07/2022 19:33

I am daring to believe our new builders are actually decent professionals. They have completed more work in 3 days then psycho builder did in a month so granted, the bar is low. Has a wobble yesterday as they said they’d be on site in the afternoon, then said they were delayed and finally called to say it they would have to come today as the job they were on was over-running. However I was also pathetically grateful for the communication and updates as psycho builder routinely disappeared for days without explanation.

Kitchen worktop finished today as builders knew a man who was able to supply and fit for £££ less than the worktop store quoted us.

OP posts:
Eastie77Returns · 16/07/2022 23:15

@Netaporter I feel so foolish and naive for paying this fraud up front for work when all the signs clearly indicated he was in financial difficulty. Live and learn.

Well I think we have now found new builders. I came upon them by chance after I popped in to visit one of our new neighbours. Her house looks absolutely stunning and she introduced me to them (father and son outfit) as they were carrying out some renovations. I surreptitiously looked them up online while I was there and read some great reviews. They are almost fully booked up over the next few months but I begged them to come and have a look at my place and the work that needs to be done (I have lost all my pride at this point). They have provided a quote for remedial and remaining work as it turns out there is thankfully not a huge amount to do and they think it can be completed in 2-3 days. Both were aghast at the poor standard of work.

Our plan to work directly with the arsehole builder’s trades fell apart. It turned out he owes them all unpaid wages and they were understandably unwilling to continue working on the house until they were paid.

He is completely banned from coming anywhere near the house after his violent threats. I’ve also compiled a dossier with photos detailing the complete shitshow that constitutes his ‘work’ on our house. There are too many defects to mention and almost all his work will have to be rectified.

OP posts:
Netaporter · 11/07/2022 13:47

@Eastie77Returns so sorry to read this. It was my original thought sadly that these were the actions of someone going bust. I hope you get the project sorted.

Eastie77Returns · 11/07/2022 13:06

So we've had to involve the police after receiving violent threats from the builder.

He called again to rant about something and I calmly asked him to tell me when he would finish work we've paid him up front for as he is yet to complete anything. He went ballistic, screamed and shouted and said if I asked him any more questions he'd come to house and "do us all over". In the meantime after doing a bit of digging online I've found a number of other customers are in the process of taking him to court. One reviewer stated they almost came to physical blows in the street. His company is also listed as status "Compulsory Strike Off" from Companies House (likely due to financial mismanagement).

The builder who put us in contact with this nutcase in the first place has apologised profusely (they are former friends). He is organising replacement help and will also come over in person to work on the unfished tasks in a week or so. Two of the tradesmen who worked for the builder have messaged to say they will work directly with us. It's almost a relief things have come to a head in this way and we've taken decisive steps to get him out of our lives.

OP posts:
Eastie77Returns · 21/06/2022 12:42

So latest update: plastering finished and looks really good. Electrics are almost there. Power U.K. and and our supplier will be out next week to finalise everything. The painter who did a fantastic job on my last property is booked in for next month. Kitchen arrives next week but not sure when (need to chase DIY kitchens)

The flooring guys started work today. They are a breath of professional air in stark contrast to the builder. I just cannot wait to see the back of him. His team of trades are amazing and the only reason we have stuck with him. Several of them have told us privately that he cuts corners and rushes things as he is juggling other jobs.

He sends me messages at 3am/4am chasing money he asked for just hours before, it is insane. I never respond at that time. Everything has to be in cash and when I explained I will not pay without a documented breakdown of costs he became annoyed and scribbled down something on the back of an envelope. When I said I could do a bank transfer quickly but going to the bank to get cash would take longer he had a complete meltdown. The level of aggression and defensiveness when we speak on the phone (he tends to be calmer in person) is completely off the scale.

Yesterday he was ranting that I’ve cost him money as he has spent his own money buying materials that he has decided not to charge me for “because you’re a nice person”. This is typically for work we had not agreed for him to do. I’m not sure why he is doing this as I’ve made it clear I will not pay for anything I have not agreed to.

Separately, he damaged part of our lovely newly installed bathroom wall with a drill. When I spoke about it to him he exploded “I’ve bought easy filler for your DP to fix that”. When I told him he must fix it he complained it is an “easy fix” and grudgingly agreed to do it. I don’t know if there are MH issues to be honest. Sometimes mid sentence he starts shouting (after starting calmly) completely out of the blue and then reverts to smiling and joking.

I know I’ve been advised to ditch him and if I could do that but keep the trades, I would. However they all seem scared of him. I calculate we will have him out of our lives in about 3 weeks.

OP posts:
Eastie77Returns · 11/06/2022 15:46

@DorothyZbornakIsAQueen thank you. I've been tearful all day. Your post has given me some hope.

Just feels so unrelenting.

OP posts:
Eastie77Returns · 11/06/2022 15:45

yourestandingonmyneck · 10/06/2022 09:56

Do you have side access to your back garden? Would it be possible to buy / rent a caravan or similar and live in the garden rather than at your parents? Means you're close to the kids schools and on site for project managing.

Just to clarify we have moved out of my parents as DC started school near the house. We rented an Air BnB short term as I was told by the builder and DP that we'd be able to move into the house next week.

Now the builder is saying it might take 6-8 weeks for the supplier to move the meter.

OP posts:
DorothyZbornakIsAQueen · 11/06/2022 15:01

We moved in to a doer Upper at the end of September. Floor to ceiling woodchip - even on the ceiling 😫. Nothing touched since the 80s. Needed rewiring etc.

Bathroom was the first thing to get done. We have just had our kitchen done and have had no running water downstairs for about a month. This was due to plastering, late delivery and wrong parts of kitchen delivered (thank you WREN - would not recommend this company to anyone)

We've been trudging upstairs washing the dinnerplates in the bathroom. We have lived off food you can cook in the ninja foodie and microwave and lots of takeaways.

Luckily there is a little lean to thing, so we had a kettle, the ninja and microwave in there.

BUT it was finished yesterday and it was worth the inconvenience. Still got the rest of the house to do, but now the kitchen and bathroom are done, the task is a million times less daunting.

There is light at the end of the tunnel OP. I actually nearly cried when I turned the tap on 😆

Eastie77Returns · 11/06/2022 14:40

Candleabra · 10/06/2022 09:56

Well that sounds a bit more positive.

At little bit more positive but not completely - see electrics update below. The builder has been around all week with a full crew. However he seems to be extremely defensive when asked any kind of question and constantly plays the victim ("I work 24/7 to help my customers and just get complaints and unreasonable demands..."). He has fallen out badly with DP and does not want him in the house when he is working there. I do understand as DP is annoying and thinks he is an expert in all matters building related. However the builder does not communicate clearly with us hence DP asking constant questions and sending lots of messages. The builder has blocked DP and will only speak directly with me.

So the electrics are not actually completed in the sense that the builder has finished the initial work but now there is a whole new round of work that has to be carried out involving our supplier, UK Power Network and an internal installation to be carried out by the electrician. This was only explained to me this morning when I reminded DP that our Air BnB booking ends next Saturday. He calmly dropped the news that there will not be any electricity in the house by then because of all this other work.

There is so much miscommunication. I clearly asked the builder if we'd be able to move into the house next week (albeit we will not have a kitchen) and he said yes.

Now it turns out that in addition to no electricity, there will be no hot water as the boiler installer says all radiators must be installed before the boiler goes up. The builder, who disagrees with every single trades who is not in his crew, says this is nonsense.

I began to cry this morning. This Air BnB is booked up after our stay so we can't extend. Where am I meant to drag the DC to next? We cannot go back to my parents as they are a few miles from the DC's new school and in London morning traffic this takes an hour plus.

OP posts:
Candleabra · 10/06/2022 09:56

Well that sounds a bit more positive.

yourestandingonmyneck · 10/06/2022 09:56

Do you have side access to your back garden? Would it be possible to buy / rent a caravan or similar and live in the garden rather than at your parents? Means you're close to the kids schools and on site for project managing.