Thanks for the positive comments!!! @RidingMyBike a start date the best date, the "end date" a moveable date. I was 50 weeks from start to move in, will be 54 week (end October) to get snagging finished. But as well as the extension, there was the complete re-wire, re-plumb, block up doors, create a new hall, move one bathroom and create and install another. Then there was the unexpected joy of rotten joists in the foundations, and more in the roof!!
I did get my bedroom finished last night with some curtains being put-up, so no more arse flashing! Not what I originally planned, but I fell in love with the wallpaper, and then had to work everything else into it!
Today is more tiling, electrician, and I am hoping a plumber, cannot keep using friends for their shower facilities - I mean they are great, but me popping in to shower at 7pm each night, is getting ridiculous!!!!