Good evening.
We are near completion of the plaster work at the end of a major house extension/ renovation. The building company is not responsible for flooring, tiling, painting and kitchen fitting. But they are doing the plumbing and electrical works.
We found it's really hard to coordinate with them from this stage as we don't know exactly what needs to be done before what and their plumber isn't very helpful in terms of educating us what suits and what not.
We are having a meeting with the project manager soon. Before that we want to understand better at this stage what lessons to learn before completion.
We want to understand the sequence of works, as some relies on the completion of others.
A few questions we have already in mind:
- shall the radiators and the boiler be fitted AFTER painting?
- shall the floor and walls be tiled first before fitting bathroom units?
- when bathroom is only tiled half way to ceiling and paint the rest, shall tiling happen first or painting happen first?
- shall the doors be fitted after painting or doesn't matter?
Any tips/advice you could share to complete this last phase, i.e. post-plaster and painting/tiling and fitting things in walls/floors.
Would be grateful if anyone can offer some insights!