Hi all,
I’m in the process of having three bathrooms refurbished (cloakroom, main bathroom, and en-suite), and I’m feeling uneasy about some issues with the tradesperson. I’d appreciate any advice or guidance!
Background:
• I requested a quote for installation, which I received by email. The subject was “Bathroom quote for [address],” and the email body also referred to it as a quote, saying, “As promised, I have attached the quote.” However, the attachment itself used the term estimate (which I've only recently discovered).
• I’ve paid 75% of the total cost so far, with the final 25% due upon completion.
The Work So Far:
• Cloakroom: First and second fix are mostly done, but there’s some snagging, decorating, and minor finishing (e.g., cupboard doors, sealant, water filter).
• En-suite: First and second fix are complete, but the shower enclosure is delayed (manufacturer issue). Some grouting and sealant are poorly done and need redoing, and a cupboard is yet to be installed.
• Main Bathroom: The main plumbing has been done, and the floor tiles are laid (but not grouted). The bath hasn’t been installed, wall tiles are yet to be started, and the shower area hasn’t been tanked.
I estimate that 65-70% of the work is complete, given the time required for the second fix.
My Concerns:
• Potential Retrospective Costs
The tradesperson recently messaged me saying he would send an email outlining “additional work” and “time-consuming materials.” However, I believe everything they’re referring to was part of the original agreed scope of work. For example:
• Tileable Bath Panel: This was in the bathroom designs provided before agreeing on the work, and we discussed it verbally during the initial site visit. The product was on-site from day one, and when I reminded him about it, he said they’d install an access panel for pipework as standard.
• Shower Taps: The plumber complained repeatedly about the taps being difficult to install and said he’d charge other customers more in the future. However, I don’t believe this is my problem. Shower taps are standard for bathroom installations, and the quote should account for challenges like this.
• <strong>Vague Scope of Work</strong>
The itemized list in the “quote” is very generic, with phrases like “full bathroom refurbishment,” “all work as discussed,” and “plastering where needed.” While we had detailed verbal discussions about the work required, these weren’t fully reflected in writing, leaving room for ambiguity.
• <strong>Overpayment vs. Work Done</strong>
While I think the work done so far aligns with the payments I’ve made, I’m nervous they’ll try to increase the cost retrospectively for things that were already discussed or within the scope of a “complete bathroom refurbishment.”
• <strong>Snagging and Quality Issues</strong>:
There’s poor grouting and sealant work in one bathroom, and I’m concerned about the standard of finish overall.
My Current Thinking:
I want to avoid unnecessary hassle, so I will pay up to £500 extra to complete the job. However, if the tradesperson wants more than this, I plan to tell them I cannot go higher and if they fail to finish the work for the agreed price, I’ll ask them to stop work whilst I look for another tradesperson to complete the job. Depending on the balance of the cost to complete the work, I’d either pay them the difference for the work done or seek a refund (even though I am unlikely to get one).
My Questions:
1. Can they legally try to increase the price now, even though all communication refers to it as a quote? I have WhatsApp messages and emails that can prove this.
2. Am I within my rights to withhold the final 25% payment until the work is complete, and all snagging issues are resolved?
3. If they propose a significantly increased price, can I ask them to leave without paying the remaining balance and get someone else to finish the work?
4. Does their complaint about the shower taps or bath panel hold any weight, given that these were part of the original plans and discussions?
I’ve been paying in cash, which they requested, and I’m now feeling anxious about how this situation could escalate. I’m waiting for their email outlining the “additional costs” to decide how to proceed, but I wanted to see if anyone has been in a similar situation or has advice on my rights.
Thanks in advance!