Morning,
We're almost at the end of a nightmare build which should've taken 12-15weeks and will hopefully be finished in week 33!! There is nothing that went right, some problems were unavoidable and understandable (e.g. hitting a sewer) and we have been incredibly patient with them. Other things have been ridiculous, for example using incorrect structural timber so we can't have the exposed beams which were a key part of the design, missing a row of bricks so the patio door was 50mm lower than the floor level (wtf!), and the obvious going over the contracted end date simply because builders weren't on site!
This really is the tip of the iceberg and although they have rectified the doors we have made a huge amount of compromises and the finish quality is still not perfect. The floorboards have been sanded and finished three times now because of incompetence, and we have now seen that the sander has damaged the sliding doors, the bespoke kitchen doors and the built in storage.
We threatened them with a £1000 fine per week over the contracted date as incentive because only one man was on site for 3 weeks, they revised the end date and we agreed to give them a further 10days (this was at 11weeks post deadline) and here we are, 4 weeks on with no one on site and one big job left to do in the last week of September.
We have a JCT homeowner contract in place and are using a FMB accredited builder - neither organisation can give us pointers on what is reasonable at this stage. We have tried the CAB, who direct us back to FMB. I was willing to let the fact they are well out of contract spec slide to have the peace but the end quality isn't what we've paid for and more importantly the sliders are likely irreparable.
Anyone had a similar issue or advice on financial penalties, if reasonable? We've got the final instalment (1/8th) to pay plus the 5% snagging.