We have just completed large building project, loft conversion and extension. Basically every room in the house was affected at some point. Project ran over massively. Our builders quote was pretty reasonable. There were always lots of workmen on site, so the overrun was not down to them as such, they were all hard workers, worked weekends etc.
Various things came up during the build that were beyond the original spec, and we knew they would be additional costs (altering size of window opemis for example, and material costs for new steels). We never got costs for these despite asking, but we're reassured by the builder who we had a good relationship with that they were going to be approx £1k, and there were a few bits we removed from the spec that we were told would balance it out.
Project finally finished and we were presented with a bill for £6k, approximately 10% of total costs. A lot of the items listed were for things that had never been discussed. For example fitting a laminate flooring upstairs. The spec our architect put together was astonishingly detailed, and to be fair, it doesn't specify that particular floor. But they just fitted it! They didn't ask if we wanted it done, and then provide a cost. They just fitted it. If I had known I would have told them not to, as I'm more than capable. Ditto some "additional painting". If I had ever been told they were painting things that were outside the spec, and that it was going to cost me £600, I would have told them not to.
Our architect was paid to administer the contract, but he's now working on another project with the builder, and I think is keen to not rock the boat with him (not my problem obviously).
Anyway, stupidly long post, sorry. I am pretty sure the builder made a loss because of the overrun, and this is his way of trying to recoup. And as a small business owner I have some sympathy. How normal is this kind of thing? Our architect seems to be suggesting it's our fault for being too informal, and that it's normal, and we should pay
Is it?