Hi. Me again. I am Girlfiend the opening poster but I have forgotten my details!
Anyway things have got Much much worse since my posting in January
The architect never produced minutes for meetings, nor did he ever provide written project budgets or projected costs when asked. So our first big shock came when we incurred £40k + of design and build fees for cupboards that we thought were included in the main contract.
Our next horror was when the architect approved the builder's requested 11 weeks extra time £16k for several items which caused him undue delay. Only one of which was to do with our requested alteration the others, strucural issues, we couldn't argue with. The point here is that we had signed a Fixed Contract. The job was supposed to be finished in a certain time, for a certain fee whatever happened.
By this time, of course, we are aware that we are dealing with a couple of shysters and have insisted on everything being in writing; all financial info requested to be provided etc. But it was a bit like closing the stable door after the horse has bolted. It is also only partially effective because arcitect has all the experience, jargon, contractual knowledge on her side). They can still run rings around us.
But, there is another pony in that there stable. Can you (architects, lawyers, QS's) help me save it. And save myself some money / illness too.
A few weeks ago the architect gave me an updated list of budgetary 'extras' which casually made mention of a new 'agreed completion date'.
No such agreement was ever made so I enquired about it - assuming a mistake. No. It was intentional. The architect was trying to transform a written enquiry about my moving dates (an email i sent in january) into a verbal discussion in which I agreed that the builders could take another 4 weeks (on top of the 11 extra weeks we had already verbally approved).
Of course, had such an agreement actuallt been made, then the builder would not have to pay us the £1000 weekly damages due in respect of any overrrun. Instead we'd have to pay them both even moreweekly fees.
Enough is enough. What can we do? The contract deadline is the end of month and though it is obvious it will overrun the builder has not yet requested a formal Extension of Time.
I am meeting arcitect next week to ask whay she intends to do if builder overruns and also to clarify what haapens in the final account process. There are so many adds and omits to negotiate and also some confusion about attendance fees in contract (kitchen) and ex contract like carpets
What do I do. She is obviously going to try some Nonsense but what I cannot predict. We are almost out of money so expensive lawyers not an option.
I am also ill following surgery this week. What do I do????