We had a very long building project that finished in April when we moved back in to our house. It was a renovation project.
We are new to the area so appointed an architect who ran the tender process to choose the builders. We picked the firm that they had the strongest recommendation for and they had worked with them before.
Long story short, the builders were a mare. The head foreman was barely on site, they missed a lot of things they shouldn't have done. Head guy would insist work had been done when it hadn't - only on our photo evidence did he finally admit certain tasks weren't done and when he finally admitted this, he would get things done.
We eventually complained to the architects who said that one of the 2 main people who run this building firm had retired without them realising and without this person, the firm was not run as well as it had been in the past. They have removed them from their recommended list.
So the works finished and there were lots of disputes about what was done/not done and I paid what I thought was the final bill in April.
The architect called me this morning to say that the builders have issued another final bill. It's several thousands of pounds (which I don't have now as I thought we had paid the final bill). She has certified the bill and says the charges are for actual works. I have pushed back and said it's ridiculous, it's too late and we weren't expecting it. The architect is now panicking because we are on a fixed price contract with the builders and she insists this is due. But as so many things overran, the final cost bears no resemblance to the final bill anyway so I had no idea we still owed money. The majority of the cost they've billed now is for a general cost x the weeks it overran (9) which is essentially a cost of the workers. It was an 8 month project so a long one.
We've said we're not paying it but I want to understand what recourse we will have. It's essentially 3 months since we moved in and the builders left and the only extra cost we were expecting was for small things like sundries that hadn't been totted up not 9 weeks of Labour cost. Incidentally during the building work, we were issued with weekly progress payments that were supposed to equal the build works that had taken place so this has come as a real shock!