Hi,
Looking for some advice/perspective as I am a bit too involved.
Essentially hired a building company ( reasonable size, not sole trader) to do renovation works on my house in July 2021.
Target finish Oct 2021.
Habitable but not finished by Jan 2022 when I moved back in. At which point I had paid 75% of the cost.
Over the last year numerous issues identified that need redoing, electrics, plastering, kitchen etc.
I hired a surveyor of my own in Feb 2022 who wrote a report that highlighted issues that needed fixing.
By October 2022 very little done, so I formally told building company that if the work was not complete to a reasonable standard by end of December 2022 I would cancel contract and go elsewhere. Not pay the 25% remaining but use it to cover rest of work and go elsewhere for builders, likely the 25% retention I hold will not cover all the work.
December 2022 they did 2 days work and asked for an extension as their builders merchants shut for xmas and needed materials.
I reluctantly agreed, and said by 16th February 2023.
You can guess the rest, no work done since, a few emails from them to say coming next week, they never do.
So today, a day before we agreed they would finish, get an email saying they might come next week!!!
If I say FO, I need new builders ( in short supply) and will have to pay extra and then recover from original builders possibly by court. Original builders quite aggressive when challenged.
So stressed and don't know what to do!