Hello Mumsnet,
I would like to ask for some general advice on some building work that has taken place at my property over the past 6 months.
I've tried as much as possible to remove any emotion from the sequence of events (although inside I've been screaming!).
We hired a firm via another firm to complete a loft conversion for us. Amazing reviews and felt in good hands from the salesperson visit. Estimate of works was 8-10 weeks (I had mentally figured 12 due to climate but they were insistent it would be 10 or less).
Work started in July 2021 and quickly seemed to fall apart....
- In the first week it was found that the architect had made some big calculation errors on construction including window placement and wall placement (meaning a different end result and damage to other parts of the house which were unplanned).
- The builders didn't secure the roof during rainy weather which caused a ceiling to collapse and water damage throughout ceilings right down to the ground floor (this hasn't been fixed).
- We have raised concerns throughout but the project manager, building firm or aggregator didn't respond or show up for arranged meetings at our property
- After 4 months the loft windows were fitted and that the work would be finished within days (it was not)
- We then (foolishly) agreed that as they had caused damage to our existing bathroom we would pay for them to replace (minus the damage) cost. They ripped out the bathroom but then didn't fit a new one - leaving us with no bathroom as the new loft one also had not been plumbed in
- In November they left with the work semi completed but to a really poor standard and missing one bathroom.
In total it has been about 32 weeks now and they have asked for final payment despite us sending a snag list about 8 weeks ago.
My question is - there is nothing out there that means we can ask for any kind of compensation or reduction due to the length of time, stress and shoddy work is there??
Thank you kindly for any advice or pointers. We do have a phone conversation today with some kind of solicitor/intermediary from the company. They kept going by email which has become messy and unproductive.