So the plan was simple:
- last Friday new electrics put in and plumbing sorted out
- Saturday - sink and toilet cistern pulled out (we now use a bucket of water to flush) and all pipes sunk into floor
- Sunday; plaster turns up late and starts at 2:30 not 9:30....so he comes again yesterday and works from 10am - 9pm last night.
Anyway he was supposed to be here at midday today - I finally get a call at 4 - he left his mobile elsewhere so couldn't reach me...blah blah got stuck on another job.....so he can come tomorrow and finish the plastering and then on Friday and start the tiling on Friday.
He was supposed to be tiling on Monday so the bathroom could be fitted out tomorrow/Thurs and finishing touches Friday if necessary. (all the new stuff is being delivered tomorrow the hallway is piled high with packs of tiles already, the fitters were due in tomorrow)
So - I know I was insane to start this project so close to having my c/s booked......I just don't know what to do....
Do I try and get another person in to finish the tiling job off tomorrow or wait....
I just can't really think straight......DH was right we should have waited.