Completion certificate timescales.

2 replies

8misskitty8 · 20/11/2014 17:33

After our extension was finished, We submitted all the certificates etc. In August It was inspected and a few things came up, minor things like seals on window etc. They also wanted a letter confirming that the open pend at the back had fireproof insulation installed (Couldn't see it as it was cladded over )
Builder returned and finished everything off, sent photos which council said was fine. Letter was sent end of October, I e-mailed them saying if anything else was needed to contact me but have heard nothing since .

How long should It take to issue me with the completion certificate ?

The council seem to be taking ages.

Thanks.

OP posts:
Report
RaphaellaTheSpanishWaterDog · 20/11/2014 17:43

We recently built a kitchen extension and had some other works also requiring building regs carried out. Our work was finished in September and we had the final inspection around the middle of the month, but like you there were a couple of things that had to be completed before sign-off.

We had the work done, submitted photos etc and received our completion certificate within just over a week......but, we used an independent building inspector, not the council which I guess makes a difference.

I'd be chasing them up.....but then I'm an impatient biatch!

Report
Marmitelover55 · 20/11/2014 19:29

I submitted everything for our extension/remodelling and inspector came within the week and we received certificate the following week. This was the council.