How much should the snagging list be?

(4 Posts)
Zippyzoppy Wed 02-Oct-13 22:54:39

Hi

We are just about to do an extension which will be around a £45k contract with builder. How much would you expect to with-hold for the snagging list?

Thanks

contortionist Thu 03-Oct-13 12:43:19

Maybe 4k; half until snagging is complete, and half for a further six months in case of latent defects.

wonkylegs Thu 03-Oct-13 13:23:19

It depends on what contract you are using. Check the small print.

askasurveyor Fri 04-Oct-13 23:10:17

Ideally pay 95% of contact sum when completed, a further 2 1/2% for immediate snagging and the final 2 1/2% after six months when defects such as shinkage cracks jave been addressed. Tjos would be tje terms of a usual minor works contract.